02 / SHUTDOWNS & OUTAGES
Planned downtime, run on a clock.
Supplemental mechanical, electrical and piping crews for annual shutdowns, planned outages and line changeovers.
SEQUENCE
T-minus planning.
- T−8 WK
Work list review
Walk the plant with your planners. Confirm the job list, trades and estimated hours.
- T−4 WK
Crew plan
Headcount by trade and shift, foremen assigned, long-lead parts and rentals flagged.
- T−1 WK
Site readiness
Orientation, permit and isolation procedures reviewed, laydown and tool cribs set.
- T−0
Execution
Shift handovers with written status. Emergent work goes through your planner before it is added.
- T+1
Startup support
Technicians stay through startup to address issues, then hand back with a close-out list.
WHAT WE BRING
Crew roles on a typical shutdown
- SHUTDOWN FOREMAN1 per crew
- MILLWRIGHTSrotating equipment
- PIPEFITTERSvalves, spools, tie-ins
- ELECTRICIANSdisconnect / reconnect
- HVAC/R TECHScooling systems
- HELPERSsupport, fire watch, cleanup
Crew sizes are set per job list.